Friday, October 7, 2016

Week 10

This week we did not meet at out at the site, but progress was coming quickly every day. On Tuesday, I meet Trevor at Plumb Supply to pick faucets. I've done my home and had narrowed the selections to Delta & Grohe. Tina was very helpful. In the end, we are going with must Grohe faucets, with a couple Delta and one Kolher thrown in.

Then, surprise! Not only are there walls, but also the flooring system. Rooms are definitely talking shape and starting to have their own feel. The kids were in the car so I was quickly running around taking pictures. Can't wait to come back and spend some more time in the space!



Very from the back corner near David's room

Looking at Kathryn's room

Back view of the house
 Back view of the house and large retaining wall
 Basement
 View out of Kathryn's room


Wednesday, September 28, 2016

Week 9

This past week was has been quite stressful. I actually wasn't at the farm till Sunday and don't think John really made it over much either. Downtown CR was preparing for flooding, second highest on record. We sandbagged most of the day Saturday. Right now the damage looks relatively minimal, but I'll still be out of my office till next Monday.

As for the house, we have wall!! The first of the framing crews has arrived, laid out the floor plates and lines, and has started building walls. The floor trusses have also arrived and are awaiting installation.

It's very very exciting to see it take more shape. Daily will be a new look and feel to the house.



One last change we made while working on windows was raising these windows up a bit. Now looking through the game room window openings, I'm so glad that we did!


Hopefully I'm able to post more picture daily. However, I'm still trying to figure out the Blogger app, it really doesn't like my droid phone. 

Sunday, September 25, 2016

I'm back...

Weeks 6 - 7 - 8

Well let's see where we left off.. oh - lumber anticipated to arrive around the 9th. Let's just say there hasn't been a whole lot to report as lumber didn't arrive till around the 19th.

That said, important work has been completed... or mostly completed. Namely, backfilling. From my perspective it does look closer to the finish grade, but as John has tried to explain very kindly several times; this is very important, even if I can't perceive the progress. We've added tile, tile, and more tile. John has made sure that Trevor's 'extra' tile was increased so that we will never experience a wet basement (remind Kathryn to thank him later as her room is in a critical spot). All of the septic connections were also made (exciting stuff!).

This is from the end of week 5

Planning with our builder, Trevor Parks

Week 6 - John inspecting the tile



Isn't tile so exciting???



Sorry I don't have more tile pictures.

On to more fun, John fixing the driver after heavy rains. 
If you would like to know what John wants for Christmas, a paved driveway is near the top of his list.


Kathryn, David, and I watched from the Mule. Kathryn was very excited to hold the flags.


Backfill!!!


More backfill!


Too better appreciate the difference, this is a picture from week 5.


Here is the similar angle at the end of week 8. Progress.




Look for the week 9 update coming soon...unless we float away first!

Funny story

So the weekend of week 6 John headed to the farm with the Kobota backhoe to drain some water away from the foundation. The kids, always interested in machines, took a wagon ride down to watch dad...


Here is John trying to create a path through the pile of dirt to drain the water



Not quite reaching far enough, John crawls the Kobota back further


This is where it gets interesting


Since there's 2 steering wheels, I went to help too.


Kathryn was very concern! David thought it was pretty cool, but also cried when sister did. 



Of course John crawled it back out. Just wish I would have got a selfie! 

Oh about that wagon ride, it's a long way around pulling 55 pounds of kids. Next time I want to ride!

Sunday, September 4, 2016

Guess Who

See if you can identify all the visitors to the house site!




Week 5

Week 5

This week started out with a huge milestone, CONCRETE! And not just any concrete, the basement floor! On Tuesday there was scattered thunderstorms, so they weighted to pour on Wednesday.




Thursday and Friday were spent tiling (adding even more drain tile around the house) and starting back filling.

On Thursday John and I meet with Tom at Electrical Concepts to discuss our Lutron bid and home automation. It was an incredibly informative and helpful to meeting to discuss how we will be using the main areas. While automation is really cool, we'll be sticking with a much more manageable and practical level.

On Sunday, John and I hunkered down and had a marathon home planning session. David slept most of the day and Kathryn had a Daniel the Tiger marathon on PBS. We are now set with our window, door, and Lutron blind selection. We also have rough sketches of the fireplaces and wet bar to hand back over to Trevor and Monica (cabinet designer).

With Monday and holiday (Labor Day), work started in earnest on Tuesday with more backfilling. Rain is in the forecast so lumber should arrive on Thursday or Friday!